This week the weather has been a bit on the cold side making work outside unpleasant but we still managed to get our water services connected and remove our scaffold steps to the plots, replacing them with stone to provide easy access for the workers on site. Off site utility works are starting w/c 17th December to lay the Gas Main and Electricity supply, the new kerb line has been marked out and the trench duct is ready for the service to be laid.
Scaffold steps removed and stone replaced, the site will look its more orderly self by the end of next week and all the service trenches can be backfilled.
We have 2 plots fully plastered and ready, our Joiners are in fixing skirting and architrave, the M&E contractor only has to pipe in the gas service to the plots, then the Dry-liners can close-up the internal ceilings ready for plastering and mist coating.