Our Groundworks Contractor has made a start digging trenches this week to enable us to lay services to the plots so that we can get Gas, Electric and Water into them before Christmas.
Both porches are now fully tiled and we are waiting the completion of the cladding to the ends and undersides of the porches, which starts next week.
The block work is being coated in the protective Render so all the façade will be ready to unveil by the end of next week with the scaffold coming down on the 5th & 6th December.
Plot 8 is ready to be plastered on Monday with our M&E contractor delivering a plot a day to the Dry-liners to close-up the internal walls ready for plastering.
Internally we have started the 1st fix M&E with 1 Flat complete and the others following on, we are looking to get the flats plastered as soon as possible.
The plan is to get all the plots skimmed before Christmas break giving the completion trades a smooth canvas for them to start installing the kitchens and bathrooms.