Monday, 4 March 2013

The deep drainage is now complete and the Hydro Brake cast in-situ manhole is ready to be concreted.


The car parking bays have been formed and the block Pavia to this area completed.


Also prepared are the cycle shed base and the bin store base. The boundary wall has been constructed just leaving the tango fencing to be fixed to it.
Inside the Flats, decoration is imminent as the electric and gas is up and running, testing is complete and the units and vinyl are protected. Most of the vinyl has been laid and the joiners only have shelving to put up and some kitchen unit ironmongery to do after decoration.