The deep drainage is all but complete only 1 manhole to construct which is to start next week; we are on with the gully connections for the new roads and parking bays working our way out of site. We are starting the construction of a retaining wall next week to tie in with half term because the wall falls on the boundary of the site and the footpath, with fewer footfalls to the school we felt it was the right time to be working along that boundary.
Our first floor flats are ready to be handed over to the decorators, just got to fill the systems with water and check for leaks before decorating can take place, all first floor systems will be filled next week and boiler fired up for the first time, 2 of the 8 flats have had the electrics checked for faults and passed so fingers crossed for the remaining 6.