This week saw the Considerate Constructor’s Assessor visit to give our site a rating in all aspects of our activities on site and our interaction with the wider community. The site scored a ‘very good site’ rating with areas where subtle changes can be made to improve our score and how as a site we can prove to be a more considerate constructor, something Wates Group Ltd are committed to.
Externals
Our Groundworks contractor has installed the main services to the plots and the off site works have started with BT placing a new duct across the road, Electric and Gas due to start w/c 17th December. Our scaffold is fully down revealing the building in all its glory, the render panels are to a nice crisp finish.
Internals
Our First Plot is being plastered with only 1 plot left for our M&E contractor to deliver. The Dry-liners are closing up the internal walls ready for plastering and Mist Coating.