Friday, 23 November 2012

We managed to survive the severe gales this week and our building is being slowly revealed, with the scaffold to the front elevation being stripped, just leaving a couple of areas up where the porches need to be tiled. The Renderer is due to start Monday to complete the external façade.


Internally we have started the 1st Fix M&E with 1 Flat complete and the others following on, we are looking to get the flats plastered as soon as possible.


Next week we have our Groundworker starting on site who will install the services in to the plots to enable us to get heat into them in order to help the internals dry-out in the cold weather that’s predicted.